126 SPARC Enterprise T5440 Server Service Manual • July 2009
2. Press the battery firmly until it snaps into place.
Next Steps
■ “Install the Service Processor” on page 122
■ “Install the Top Cover” on page 150
■ “Slide the Server Into the Rack” on page 151
■ “Connect the Power Cords to the Server” on page 153
■ “Power On the Server” on page 153
Servicing the Power Distribution Board
Main 12V power is connected to the motherboard through a bus bar. Standby power
and other control signals are routed through the flex cable circuit to the motherboard.
Related Information
■ “Safety Information” on page 59
■ “Servicing Power Supplies” on page 85
▼ Remove the Power Distribution Board
Before you begin, complete these tasks:
■ Read the section, “Safety Information” on page 59.
■ Power off the server using one of the methods described in the section, “Powering
Off the System” on page 63.
■ “Disconnect Power Cords From the Server” on page 65
■ “Extend the Server to the Maintenance Position” on page 66
■ “Remove a Power Supply” on page 89
Note – You must remove all four power supplies from the system.
■ “Perform Electrostatic Discharge – Antistatic Prevention Measures” on page 69
■ “Remove the Top Cover” on page 69
Do the following:
Comentários a estes Manuais